A new TP ACS technology!
Works
 
  Due Date Customer/General Subcontractor Object Short Description of the Work Performed
Ventspils nafta, Jsc
reception of oil and oil products from pipelines and tank wagons, storage, loading to tankers
01/20 — 04/20 “Ventspils nafta” terminals, Ltd / Company infrastructure Revision of design solutions for Ventspils nafta oil product pipeline preservation and dismantling works in Ventspils, Latvia
10/19 — 12/19 “Ventspils nafta” terminals, Ltd / Company infrastructure Modernisation of the emergency stop system (ESD) for technological process pump stations No.4, No.5 and pentane pumping station
08/19 — 04/20 “Ventspils nafta” terminals, Ltd / Company infrastructure Designer’s supervision of vapor disposal pipeline construction on rail tank unloading facility No.3 (Ventspils nafta terminâls, Ventspils)
07/19 — 02/20 “Ventspils nafta” terminals, Ltd / “Ventspils nafta” terminals, Ltd Connection of loading unit (MLA) to VNT security system (design and software development)
05/19 — 10/19 “Ventspils nafta” terminals, Ltd / Company infrastructure Upgrade (version 7.1 to 8.1) of top level of SCADA software (Ventspils nafta terminâls)
05/19 — 07/19 “Ventspils nafta” terminals, Ltd. / Company infrastructure Development of SCADA software and wiring diagrams for substitution of pump No.401 (TSS5) with pump No.68 (TSS2) (Ventspils nafta terminâls)
02/19 — 03/19 “Ventspils nafta” terminals, Ltd / The railway rack No.3 Design solutions for the gas pollution monitoring system on the railway rack No.3
02/19 — 03/19 “Ventspils nafta” terminals, Ltd./ / The railway rack No.4 Design solutions for the gas pollution monitoring system on the railway rack No.4
08/18 — 11/18 Ventspils nafta” terminals, Ltd / The railway rack No.3 Construction design of vapour return pipeline from railroad tank car loading rack No.3 (Ventspils nafta" terminâls ltd.)
01/18 — 06/18 “Ventspils nafta” terminals, Ltd / Company infrastructure Development of SCADA software for process pipelines and vapour emission control system
10/17 — 05/18 “Ventspils nafta” terminals, Ltd / Company infrastructure Construction of process pipelines, designer’s supervision
09/17 — 05/18 Ventspils nafta” terminals, Ltd / Company infrastructure Designer supervision of construction of oil vapour recovery system applied during tank vessel loading operations
08/17 — 05/18 “Ventspils nafta” terminals, Ltd / Company infrastructure Construction and technological process solutions for fuel oil vapour recovery on jetty No.3
02/17 — 08/17 Ventspils nafta” terminals, Ltd / Company infrastructure Construction design: oil transport pipelines in “Ventbunkers” JSC rented area
11/16 — 12/16 Ventspils nafta” terminals, Ltd / Company infrastructure Potential hydroblow assessment in process lines and pump station
09/16 — 12/16 “Ventspils nafta” terminals, Ltd / Company infrastructure Installation design for tank Nr.108 floating roof
04/16 — 04/17 Ventspils nafta” terminals, Ltd. / SZMA V” JSC Company infrastructure Process and structural design parts for refitting of Ventspils Nafta Ltd. storage tanks 121 and 122 for loading and storage of gasoline and related products
02/16 — 07/17 Ventspils nafta” terminals, Ltd / Company infrastructure Construction design: construction of vapor recovery system (applied for marine unloading operations) and recovery system pipelines.
12/15 — 06/16 "Ventspils nafta” terminals, Ltd / Lakalme Ltd Company infrastructure Development, installation and commissioning of dedicated and auxiliary equipment for the construction and connection from the existing flotation equipment SCADA software package for GEA equipment visualization and control/monitoring of other automated process equipment.
06/15 — 07/15 “Ventspils nafta” terminals, Ltd / Company infrastructure Engineering design for construction of dedicated and auxiliary equipment and its connection from the existing flotation equipment SCADA distribution unit.
03/15 — 07/15 Ventspils nafta” terminals, Ltd. / Company infrastructure Migration of wastewater treatment unit’s SCADA by replacing the existing medium-level controller AutoLog2000S with the TSX Quantum controller in the sewage pumping station.
08/13 — 05/15 “Ventspils nafta” terminals, Ltd. / Company infrastructure Supervision of in-site process pipeline junction reconstruction works
04/13 — 08/13 “Ventspils nafta” terminals, Ltd. / Company infrastructure Engineering design documenation for butanization facility modernization project
01/13 — 07/13 “Ventspils nafta” terminals, Ltd. / „SZMA V” JSC Pump station No.2 Design and setup of 6 kV electrical installations, software. Technological process setup
12/12 — 06/13 “Ventspils nafta” terminals, Ltd./ / Company infrastructure Feasibility study of buthanization facility modernization scenarios
09/12 — 02/13 “Ventspils nafta” terminals, Ltd / Company infrastructure Development of construction design for internal process pipes junctions
08/12 — 06/13 “Ventspils nafta” terminals, Ltd. / Pump station No.2 Reconstruction supervision of process pump station No.2
07/12 — 11/12 “Ventspils nafta” terminals, Ltd. / „SZMA V” JSC Pump station No.4 Developmet and start-up of upgraded versions of APCS and energy ACS software. Process equipment commissioning
02/12 — 11/12 “Ventspils nafta” terminals, Ltd. / „SZMA V” JSC Pump station No.3 6 kV electric equipment, software development and start-up, process equipment commissioning
02/12 — 12/12 “Ventspils nafta” terminals, Ltd / Pump station No.4 Reconstruction supervision of process pump station No.4
11/11 — 12/11 “Ventspils nafta” terminals, Ltd / Company infrastructure Leak detection software development
09/11 — 12/12 “Ventspils nafta” terminals, Ltd / Railway unloading platform No.4 Engineering design for heating units alteration and development of software for vapor recovery system
09/11 — 11/12 “Ventspils nafta” terminals, Ltd / Company infrastructure Development of engineering design for construction of new pipeline route from “Ventspils nafta” terminâls ltd. territory to oil jetties
07/11 — 10/12 “Ventspils nafta” terminals, Ltd / Pump station No.3 Supervision of process pump station No.3 reconstructio process.
06/11 — 02/12 “Ventspils nafta” terminals, Ltd / Company infrastructure Engineering design for Expansion of industrial waste water pre-treatment facilities.
08/10 — 06/11 “Ventspils nafta” terminals, Ltd / Pump stations No. 2,3,4 Engineering design for reconstruction of Pump stations No.2-No.4
08/10 — 02/11 “Ventspils nafta” terminals, Ltd. / Company infrastructure Development and approval of engineering design project for vapor recovery system of ,„Ventspils nafta” terminâls” Ltd. Design supervision
08/10 — 10/10 “Ventspils nafta” terminals, Ltd / Berths No.2,3 Automation solutions of berths No.2, No.3.
05/10 — 10/10 “Ventspils nafta” terminals, Ltd. / „SZMA V” JSC Company infrastructure Software development, adjustment and commissioning for „Ventspils nafta” terminâls” pump station located in Ventspils, Talsu str. 75
04/10 — 12/11 “Ventspils nafta” terminals, Ltd. / ZRF „Rumba” Ltd. Company infrastructure Construction and installation works, procurement of materials and equipment for „Ventspils nafta” terminâls” piping system
12/09 — 02/10 “Ventspils nafta” terminals, Ltd. / Pump station No.6a Engineering design of pump station No.6 located in “Ventspils nafta” terminâls” rented area.
11/09 — 05/10 “Ventspils nafta” terminals, Ltd / Platform No.1 Development of joint automatic process control centre (APCS) for “Ventspils nafta” terminals, Ltd.
11/09 — 04/10 “Ventspils nafta” terminals, Ltd. / A-Servis Group Ltd. Company infrastructure Procurement, installation and commissioning of fire detection and fire-fighting equipment
11/09 — 12/09 “Ventspils nafta” terminals, Ltd. / A-Servis Group Ltd. Company infrastructure Engineering design of communication channel connecting the pieres located at Dzintaru str. 90 (Ventspils) and pieres in “Ventspils nafta” terminâls” area (Talsu str.75, Ventspils). Procurement, installation works, commissioning.
10/09 — 12/09 “Ventspils nafta” terminals, Ltd / Company infrastructure Engineering design of pipeline construction in “Ventspils nafta” terminâls” rented area.
10/09 — 10/09 “Ventspils nafta” terminals, Ltd. / Storage tanks No. 401-410 Engineering design of replacement and re-location of foam generators of storage tanks No.401 - 410
05/09 — 06/10 “Ventspils nafta” terminals, Ltd / Platform No.1 Development of joint automatic process control centre (APCS) for “Ventspils nafta” terminals, Ltd./
04/09 — 09/09 “Ventspils nafta” terminals, Ltd / Company infrastructure Construction design „Newly-designed pipeline corridor from Ventspils Nafta territory to oil berths. Pipeline section No.4 on „Ventbunkers“ JSC territory. Editing and re-approval of the documentation“.
04/09 — 08/09 “Ventspils nafta” terminals, Ltd / Company infrastructure Development of engineering design of „“Ventspils nafta” terminals, Ltd.“ pump station No.9
04/09 — 08/09 “Ventspils nafta” terminals, Ltd / Company infrastructure Development of engineering design of the project „“Ventspils nafta” terminals, Ltd.“Butanization facilities complex“
03/06 — 12/10 “Ventspils nafta” terminâls, Jsc. / Dispatching office Supervision of development of an information system for the dispatching service
Ventbunkers, Jsc
reception from pipeline and tank wagons, storage and loading to tankers
05/18 — 07/18 Ventbunkers, Jsc / Company infrastructure Designer supervision of construction of fuel oil vapor emission control system
04/18 — 05/18 Ventbunkers, Jsc / Company infrastructure Construction design for reinstallation of underground steam line on the existing supports
02/18 — 03/18 Ventbunkers, Jsc / Company infrastructure Design of construction of fuel oil vapor emission control system
09/17 — 12/17 Ventbunkers, Jsc / Company infrastructure Minimum scope construction design of the emission control system for collecting fuel oil vapours from tankers and transporting to the absorption plant
05/17 — 06/17 Ventbunkers, Jsc / SZMA V” JSC Company infrastructure Process and construction design for diesel fuel pipeline DN 300 substitution project
04/17 — 05/17 Ventbunkers, Jsc / Company infrastructure Diesel fuel marking tanks No.29.2 detailed design scope development
10/16 — 02/17 Ventbunkers, Jsc / Company infrastructure Reconstruction of wastewater treatment unit’s automatic process control system
05/16 — 07/16 Ventbunkers, Jsc / SZMA V” JSC Company infrastructure Development of process design and construction design parts of the " Ventbunkers JSC diesel fuel bunkering system" design project
03/15 — 06/15 Ventbunkers, Jsc / Company infrastructure Design of the technological process, construction, electrical and technological process automation parts for the design project of replacement of pipelines in the pump house No. 2
06/09 — 11/09 Ventbunkers, Jsc / Company infrastructure Construction supervision of installation of process pipelines for diesel fuel mixing and grading in tanks No.29.2, No.29.4.
06/09 — 11/09 Ventbunkers, Jsc / Company infrastructure Engineering design of construction of diesel fuel transhipment system
02/09 — 03/09 Ventbunkers, Jsc / Company infrastructure Development of engineering design of connection of tanks No.12, no.13 to pumps station No.32.
11/08 — 06/09 Ventbunkers, Jsc / Company infrastructure Engineering design of diesel oil mixing and grading unit construction
10/08 — 02/09 Ventbunkers, Jsc / Company infrastructure Supervision of fire-protection equipment installation on the existing railway loading/unloading platform.
08/07 — 03/09 Ventbunkers, Jsc / Company infrastructure Engineering design of bunkerage technology system
LatRosTrans, Ltd
oil and oil products storage and transportation
07/19 — 11/19 “LatRosTrans” Ltd / Ilukste Pipeline Service Station Development of SCADA rejuvenation design, 2nd stage
03/19 — 07/19 “LatRosTrans" Ltd. / Ilukste Pipeline Service Station Ilukste Pipeline Service Station. Reconstruction of automatic fire suppression utilities
07/18 — 12/18 LatRosTrans, Ltd / Development of automated dispatch control system
07/18 — 08/18 LatRosTrans, Ltd / Ekolat Ltd Dzukste Pipeline Service Station Reconstruction of station’s water treatment system. Automation system
07/18 — 07/18 LatRosTrans, Ltd / Ekolat Ltd Ilukste Pipeline Service Station Reconstruction of industrial storm water sewerage system and process pipelines drainage system
06/18 — 11/18 LatRosTrans, Ltd / Designer supervision of reconstruction of backup pipeline crossing Musa rives (292 – 293 km section of main oil pipeline Polotsk- Ventspils) and construction of the access road
09/17 — 12/17 SIA “LatRosTrans” / Development of automated operational dispatch control system rejuvenation design
07/17 — 11/17 /
07/17 — 11/17 LatRosTrans, Ltd / Ilukste Pipeline Service Station Reconstruction of Ilukste Pipeline Service Station SCADA system (top and medium level)
11/16 — 03/17 LatRosTrans, Ltd / Ilukste Pipeline Service Station Optimization of the technical design for the reconstruction of the automatic fire-fighting system of the "Ilûkste" PSS, project phasing according to the schedule of technical inspections, calibration and repair works
10/16 — 12/17 LatRosTrans, Ltd / Reconstruction of the backup pipeline under the river Mûsa (a part of main oil pipeline "Polotsk-Ventspils" (292, 293 km)) and improvement of the access to the site
10/16 — 11/16 LatRosTrans, Ltd / Ilukste Pipeline Service Station Development of technical design for reconstruction of PPS "Ilûkste" storage tanks.
08/16 — 12/16 LatRosTrans, Ltd / Ilukste Pipeline Service Station Technical design for the modernization of main pump units control and power supply diagram.
08/16 — 12/16 LatRosTrans, Ltd / NPS “Skrudaliena” Development of APCS reconstruction design
10/15 — 11/15 LatRosTrans, Ltd / NPS “Skrudaliena” Development of APCS reconstruction design
10/15 — 11/15 LatRosTrans, Ltd / Ilukste Pipeline Service Station Development of APCS reconstruction design
08/15 — 11/15 LatRosTrans, Ltd / NPS “Skrudaliena” Front-end engineering for optimization of NPS “Skrudaliena”
07/15 — 08/15 LatRosTrans, Ltd / Ekolat Ltd Ilukste Pipeline Service Station Water supply system reconstruction : re-design of automation part, designer’s supervision
11/14 — 03/15 LatRosTrans, Ltd / Dþûkste oil transshipment facility Automatic process control system modification
06/14 — 10/14 LatRosTrans, Ltd / Ilukste Pipeline Service Station Design of modification of automatic fire suppression system
10/13 — 04/14 LatRosTrans, Ltd / Ventspils Reception Point Refurbishment of automatic process control system for diesel fuel fiscal metering unit
09/13 — 10/13 LatRosTrans, Ltd / Ilukste Pipeline Service Station Ilukste Pipeline Service Station ACS medium and top layer software upgrading
10/12 — 01/13 LatRosTrans, Ltd / Ventspils Reception Point Reconstruction design for diesel fuel accounting automatic process control system
08/12 — 10/12 LatRosTrans, Ltd / Ilukste Pipeline Service Station Reconstruction design of internal transshipment pipelines
08/10 — 10/10 LatRosTrans, Ltd / Ilukste Pipeline Service Station Development of engineering design for temporary shut-down of Ilûkste pipeline service station
03/10 — 03/10 LatRosTrans, Ltd / Ilukste Pipeline Service Station Upgrading of “Account” software complex
02/10 — 07/10 LatRosTrans, Ltd / Sketch design of simplified reconstruction of company facilities and control centre
Ventamonjaks, Jsc, Ventall Terminals, Ltd
reception of oil products and chemicals from tank wagons, storage and loading to tankers
05/19 — 05/19 VK Terminal Services / Company infrastructure Front-end reconstruction design of piping and valves of the existing tanks No. 21/1-21/6, 446, 447 for adjustment to operations with palm oil (VK Terminal Services)
04/19 — 04/19 VK Terminal Services, Ltd / EMEROL, Ltd Company infrastructure Development of concept and construction design for installation of pig launching/receiving units of pipelines L-2, L-5 (VK Terminal Service)
03/19 — 04/19 “Ventall Terminâls” Ltd / Company infrastructure Reconstruction design of foam fire extinguishing system of rail truck unloading facilities on rail lines No. 5, 6, Nr.13, 14 (Ventall Terminals)
01/19 — 07/19 “Ventamonjaks”, Ltd / Company infrastructure Development of the minimum scope design for Modernization of the automated process control system (SCADA) of the ammonia transshipment facility ("Ventamonjaks") and front-ent design for selection of Siemens controller equipment
11/18 — 11/18 VK Terminal Services, Ltd / Latus SARDZE, Ltd Company infrastructure Design of construction structures for foundations of fire pumps No. 24/1, 24/2 (VK Terminal Services)
08/18 — 09/18 VK Terminal Services, Ltd / Company infrastructure Development of design documentation for the construction of oil vapour recovery pipeline from existing vacuum pumps to jetty No.35
08/18 — 09/18 VK Terminal Services, Ltd / Company infrastructure Development of reconstruction design for fire-fighting technology process of the existing automatic fire fighting pump sattion (VK Terminal Services)
04/18 — 04/18 “Ventamonjaks serviss”, Ltd / Company infrastructure Front-end (pre-design) engineering for re-equimpent of the existing infrastructure for operations with palm oil (loading from tanker ships , storage, loading to railway tanks)
06/17 — 12/17 Ventamonjaks serviss”, Lt / Company infrastructure Installation supervision of firefighting pumps and diesel engines installation as a part of automatic fire fighting station modernization project
04/17 — 03/18 “Ventamonjaks serviss”, Ltd / Company infrastructure Front-end engineering works for instrumentation substitution
05/16 — 06/16 “Ventall Terminâls” Ltd / Company infrastructure Development and approval procedures of documentation for the modernization of the automatic firefighting pumping station, installation of fire extinguishing pumps with diesel engines
04/16 — 06/16 “Ventall Terminâls” Ltd / Company infrastructure Audit and proposals for modernization of the existing SCADA
03/16 — 08/16 Ventamonjaks serviss” Ltd / Company infrastructure Development and approval procedures of the construction design documentation for the reconstruction of the fire-fighting pipelines of "Ventamonjaks serviss" LTD directed from the fire pump station to the unloading facilities on rail lines No.2, 15
05/14 — 12/14 “Ventall Terminâls” serviss” Ltd / Company infrastructure Design documentation for installation of two vacuum pumps under modification project of vacuum pump station
08/10 — 12/10 “Ventamonjaks”, Jsc / MBC.Metrology Bureau Consulting, Ltd Company infrastructure Development of technical documentation for replacement of secondary control and monitoring equipment of compressor (pos.C-1A,B, C, D), II stage
08/10 — 12/10 “Ventamonjaks serviss” Jsc / Company infrastructure Modernization design for fire extinguishing system
04/10 — 09/10 “Ventamonjaks”, Jsc / MBC.Metrology Bureau Consulting, Ltd Company infrastructure Replacement of compressors’ secondary monitoring and control instruments (pos.C-1A, B, C, D) : replacement of equipment and materials, installation works, software development, commissioning.
02/10 — 03/10 “Ventamonjaks”, Jsc / MBC.Metrology Bureau Consulting, Ltd Company infrastructure Development of technical documentation for replacement of secondary control and monitoring equipment of compressor (pos.C-1A, B, C, D)
07/09 — 12/09 “Ventamonjaks”, Jsc / MBC.Metrology Bureau Consulting, Ltd Company infrastructure Replacement of secondary control and monitoring equipment of compressor (pos.C-1B,C) - replacement of equipment and materials; installation works; development, installation and start-up of software.
Conexus Baltic Grid,Jsc / Gaso, Jsc / Latvijas Gaze, Jsc
gas transport, storage and distribution
01/20 — Conexus Baltic Grid, Jsc/ / Inchukalns Underground Gas Storage Construction design and supervision for renovation of Inèukalns Underground gas storage gathering station No. 3 (dismantling of existing station and construction of new gas gathering station)
06/19 — Gaso, Jsc / Company infrastructure Delivery, assembly, adjustment, calibration and commissioning of gas chromatograph
06/19 — Conexus Baltic Grid, Jsc / GRS "Brocçni" Reconstruction of gas regulation station “Broceni”
06/19 — Conexus Baltic Grid, Jsc / Company infrastructure Designer’s supervision of reconstruction of valve station T3/T4 of the main gas pipeline Viresi – Tallinn
06/19 — Conexus Baltic Grid, Jsc / Company infrastructure Designer’s supervision of reconstruction of GRS Broceni with substitution of the process equipment
06/19 — Conexus Baltic Grid, Jsc / Inchukalns Underground Gas Storage Reconstruction of gas metering station KS-1 of Incukalns Underground gas storage
06/19 — Conexus Baltic Grid, Jsc / Company infrastructure Designer’s supervision of reconstruction of the main gas pipeline branch directed to GDS Sloka with substitution of pipes on 22.6êm-30.6êm section
05/19 — 07/19 /
04/19 — 09/19 Conexus Baltic Grid, Jsc / Company infrastructure Development of reconstruction design for the main gas pipeline branch to the Valmiera-1 GRS and junction to the Vireshi-Tallinn main gas pipeline
01/19 — 12/19 Conexus Baltic Grid / Company infrastructure Renovation of 4 (four) gas production wells (No. 59, 70, 74 and 87) at JSC Inèukalns Underground Gas Storage of JSC "Conexus Baltic Grid"
01/19 — 08/19 Conexus Baltic Grid, Jsc / Company infrastructure Development of the reconstruction design for the valve station T5-T6 of the main gas pipeline Viresi-Tallinn
12/18 — 06/19 Conexus Baltic Grid / Inchukalns Underground Gas Storage
12/18 — 12/18 Conexus Baltic Grid, Jsc / Inchukalns Underground Gas Storage
10/18 — 06/19 /
09/18 — 06/19 Conexus Baltic Grid, Jsc / GDS Riga-3 Development of the design solutions for increasing of the throughtput capacity of the reduction line of GDS Riga-3; designer supervision.
04/18 — 12/18 Conexus Baltic Grid / GDS Broceni
04/18 — 10/18 Conexus Baltic Grid, Jsc / Company infrastructure Reconstruction design of valve station T3/T4 of the main gas pipeline Viriesi – Tallinn
03/18 — 07/18 Conexus Baltic Grid, Jsc / Ernst & Young Baltic Ltd Feasibility study and financial analysis of gas transportation extension between Latvia and Lithuania
02/18 — 02/19 Conexus Baltic Grid, Jsc / Inchukalns Underground Gas Storage Designer supervision of construction of valve station No.91 (IUGS)
11/17 — 08/18 Conexus Baltic Grid, Jsc / Company infrastructure Reconstruction design of the main gas pipeline branch directed to GDS Sloka with substitution of pipes on 22.6êm-30.6êm section
11/17 — 12/18 Conexus Baltic Grid, Jsc / Gas measurement station "Korneti" Reconstruction of metering unit and controllers unit of Korneti commercial gas accounting station
11/17 — 02/18 Conexus Baltic Grid, Jsc / GDS Jelgava -1 GDS Jelgava -1 reconstruction design with substitution of process equipment
11/17 — 12/17 Conexus Baltic Grid, Jsc / Company infrastructure SCADA development for GDS odorization system
08/17 — 10/17 Conexus Baltic Grid / KATLINIEKS Ltd. Company infrastructure Development of work implementation plan for preparation of main gas pipeline branch directed to GDS Jelgava-2for internal diagnostics
07/17 — 09/19 Conexus Baltic Grid, Jsc / Gas gathering station No.2 Reconstruction of gas gathering station No.2. Construction supervision
06/17 — 09/19 Conexus Baltic Grid, Jsc / Baltijas Energo Bûve Gas gathering station No.2 Reconstruction of gas gathering station No.2
03/17 — 12/18 Conexus Baltic Grid, Jsc / Company infrastructure Designer supervision of construction of IUGS connection point (LG-267-5) and pig launching station on the border with Lithuania (LG-267-4).
01/17 — 09/17 Latvijas Gâze, Jsc / Company infrastructure Gas reduction stations (GRS) Sloka , GRS Saldus, GRS Liepaja, GRS Jekabpils, GRS Daugavpils : delivery, installation, start-up, adjustment, calibration and commissioning of commercial operation of container-type gas quality points (GCP) with a gas chromatograph, O2 detection unit and gas moisture detection unit
01/17 — 05/17 Latvijas Gâze, Jsc / Company infrastructure Procurement, installation, calibration, start-up and commercial commissioning of gas metering instrumentation of Korneti gas reducing/metering station
09/16 — 06/17 Latvijas Gaze, Jsc / Compression station No.2 Delivery of spare parts, training of personnel, assembly of measuring station equipment in compression room No.2, programming, testing and commissioning of the complete system.
04/16 — 12/16 Latvijas Gaze, Jsc / Company infrastructure EPC reconstruction (procurement, installation, commissioning, regulation, calibration and commercial commissioning of 6 gas distribution stations for the installation of gas quality metering units (including gas chromatograph, oxygen analyzer, H20 dew point analyzer, probe unit) at the following stations: GRS Iecava - Liepaja, GRS Ogre, GRS Vaimiera-1, GRS R-1, GRS Ziemieli, GRS Cesis supply
04/16 — 12/16 Latvijas Gaze, Jsc / Compression station No.2 Inchukalns underground gas storage: reconstruction design of valve unit No.91 of compressor station No.2
04/16 — 12/16 Latvijas Gaze, Jsc / Company infrastructure Designer’s Supervision of the following objects: "Reconstruction of valve unit No. Iz225 of gas pipeline Izborsk -Inchukalns UGS; „Reconstruction of valve unit No. Iz227 of gas pipeline Izborsk -Inchukalns UGS”; „Reconstruction of junction unit connecting gas pipeline Upmala -Preili –Rezekne with gas pipeline Riga – Daugavpils”; „Gas regulations station (GRS) Sloka reconstruction with installation of existing equipment in GRS container - Jurmala, Graudu street 8".
03/16 — 12/16 AS “Latvijas Gâze” / Company infrastructure Designer’s supervision of the repair works of High Pressure (P-6) above-ground gas pipeline DN 700 mm , average pressure (P <4 bar) above-ground gas pipeline DN 250 mm and DN 150 mm in Riga "(RE-0002-14 (4 )) "
02/16 — 07/17 Latvijas Gaze, Jsc / Pietro Fiorentini S.p.A. Gas gathering station No.2 Reconstruction of Incukalns UGS gas gathering station No.2: development of technical documentation, procurement of SCADA systems, equipment and materials for the power supply system
02/16 — 03/16 Latvijas Gaze, Jsc / Company infrastructure Development of technical documentation for the manufacturing and installation of a cathodic protection SCADA system telemechanical control cabinet
11/15 — 12/15 Latvijas Gaze, Jsc / Compression station No.2 Supervision of construction works during the reconstruction of the oil tank building of Incukalns UGS compressor station No.2"
08/15 — 04/16 Latvijas Gaze, Jsc / Company infrastructure Feasibility study for commercial accounting unit of gas transportation system
08/15 — 12/15 Latvijas Gaze, Jsc / Company infrastructure Construction design of cleaning and smart pig launching unit for the Riga-Panevezys gas pipeline. Control and automation systems. Technological communications
04/15 — 12/15 Latvijas Gaze, Jsc / Company infrastructure Supervision of construction works: "Construction of valve unit of the gas pipeline Iecava-Liepaja and reconstruction of junction unit of gas pipeline branch to GRS " Nakotne
04/15 — 12/15 Latvijas Gaze, Jsc / -- Company infrastructure esign projects : "Reconstruction of valve unit No. Iz225 of gas pipeline Izborsk -Inchukalns UGS; „Reconstruction of valve unit No. Iz227 of gas pipeline Izborsk -Inchukalns UGS”;; Reconstruction of junction unit connecting gas pipeline Upmala -Preili –Rezekne with gas pipeline Riga – Daugavpils”; „Construction of cleaning and smart pig launching unit for the Riga-Panevezys gas pipeline”; Reconstruction of junction unit connecting gas pipelines Pskov - Riga, Izborsk -Incukalns PUGS, Riga - Incukalns I-line and Riga - Inèukalns II-line with Inèukalns Underground Gas Storage; Reconstruction of Sloka Gas Regulating Station (GRS) with the installation of existing equipment in the GRS container.
03/15 — 12/15 Latvijas Gaze, Jsc / Company infrastructure Development of technical solutions for repairs of high pressure (P<6 bar) overground gas pipeline Dn700 mm and average pressure (P<4 bar) overground gas pipelines Dn250 mm and Dn150 mm in the area of Salaspils, Krustpils, Rencçnu un Lubânas streets (Riga)
03/15 — 12/16 Latvijas Gaze, Jsc / Korneti gas metering station Feasibility study for reconstruction of station’s metering lines
02/15 — 12/15 Latvijas Gaze, Jsc / Company infrastructure Construction supervision of adjusting main pipeline Vilnius-Riga 445.605 km – 489.055 km section and related branches to operation pressure up to 1.6 MPa
01/15 — 05/15 Latvijas Gaze, Jsc / Compression station No.2 Design for substitution of two oil tanks in IUGS compression station No.2
JSC "RIGAS SILTUMS"
12/16 — 05/17 JSC "RIGAS SILTUMS" / “Imanta” heating plant “Imanta” heating plant municipal water supply and sewerage system reconstruction design development works
09/16 — 12/16 JSC "RIGAS SILTUMS" / “Imanta” heating plant Technical design of gas metering station for Imanta heating plant
Juras projekts, Ltd
04/19 — CHR Design Solutions, Ltd / Free port of Ventspils Designer’s supervision of particular parts of Free port of Ventspils Northern pier restoration design
02/18 — 08/18 Ventspils free port / Ventspils free port Relocation of the existing cables , development of electrotechnical, control and automation, cable rack structure design solutions for the reconstruction of the Northern pier of Ventspils free port
07/13 — 12/13 Juras projekts, Ltd / Development of “Krievu Sala” infrastructure General layout diagram for infrastructure development
03/09 — 08/09 Juras projekts, Ltd / Development of documentation related to construction solutions of engineering design “Typical construction solutions for elevated passenger platform”.
05/08 — 01/09 Juras projekts, Ltd / Kundzinsala multifunctional terminal Prospective general layout , engineering design of I phase 1st stage, extended draft design and engineering design of I phase 2nd and 3rd stages. Approval of documents.
07/07 — 12/09 Juras projekts, Ltd / Development of “Krievu Sala” infrastructure Draft and engineering design (general layout)
Kundzinsalas dienvidu projekts, Ltd
09/17 — 05/18 Kundzinsalas dienvidu projekts, Ltd / Development of a minimum scope construction design and obtaining the construction permit for the Liquefied gas terminal in the area of the Free port of Riga, Kundzinsala island
06/06 — 12/09 Secretariat of Special Assignments Minister for Electronic Government Affairs / State Integrated Information System Arrangement and support of State Integrated Information System (1 stage)
05/06 — 12/09 Secretariat of Special Assignments Minister for Electronic Government Affairs / State Integrated Information System Improvement of the State integrated information system (2 stage)
E2C, Ltd
11/17 — 03/19 E2C, Ltd / Development of minimum scope construction design and obtaining of construction permit for Liquified natural gas terminal in Liepaja
07/08 — 12/09 LR Iekslietu ministrijas Informacijas centrs / Latvian Ministry of Interior Modernization and testing of 2nd generation Schengen information system software and related registers.
Rinuzi Oil Terminal
07/15 — 09/15 “Naftimpekss”, Ltd. / Rinuzi Oil Terminal Software modernization
02/11 — 07/11 “Naftimpekss”, Ltd / Rinuzi Oil Terminal On-site supervision of construction project “Expansion of Light oil tank farm”
03/10 — 10/10 SZMA-Riga, Ltd / Upgrading of Naftimpekss, Ltd. tank farm “Unipark” automated control system
11/09 — 12/10 “Naftimpekss”, Ltd / Rinuzi Oil Terminal Construction supervision of 27500 m3 oil storage tank
06/09 — 07/11 “Naftimpekss”, Ltd. / Rinuzi Oil Terminal Design works for the project of installation of 4 additional tanks in Rinuzi oil terminal.
RIXJET Riga, Ltd
10/16 — 12/16 “RIXJET Riga” Ltd ' / Tank farm Design, commissioning and hardware procurement for the Control system
09/13 — 12/13 CEMEX, Ltd / Cement works in Broceni Engineering design documentation for substitution of reducer No. 5
06/08 — 10/10 SNEF Latvia / Cement works in Broceni Supply of materials, installation of plants and equipment, testing
LR State Agency for Defence Properties
11/19 — State Agency for Defence Properties / NATO Support and Procurement Agency “Lielvarde” air base Detailed design development and author supervision for Passenger terminal, Lielvarde air base
04/19 — 09/19 State Agency for Defence Properties / Feka Construction “Lielvarde” air base Detailed design development and author supervision for following projects of Lielvarde air base: Motorpool; Battalion building; Repair Admin Area Access Road
01/18 — 07/18 State Agency for Defence Properties / “Lielvarde” air base Design and supervision of fuel storage facility shelter of the Natiolal Airforce base
10/17 — 03/18 State Agency for Defence Properties / “Lielvarde” air base Design and supervision of fuel storage facility shelter of the Natiolal Airforce base
05/17 — 08/17 State Agency for Defence Propertie / Engeneering S.r.l. “Lielvarde” air base Rotary wing aircraft infrastructure design for USA air forces
07/15 — 08/15 State Agency for Defence Properties / “Lielvarde” air base Amendments of the technical design of jet fuel storage facility in Lielvarde
06/09 — State Agency for Defence Properties / “Lielvarde” air base Development of construction design for jet fuel storage facilities in Ogre district. Construction supervision.
Ventspils Free Port administration
04/12 — 12/15 Ventspils Free port administration / Ernst&Young Baltic, Ltd Analysis and provision of information in connection with the optimum technological solutions of the facilities to be constructed in Ventspils free port area: -Liquefied natural gas bunkerage terminal - Oil-contaminated waste-water treatment plants
04/12 — 01/14 Ventspils Free port administration / 5AM, Ltd Feasibility studies and technical specification for jetty electrification project in Ventspils free port area
04/12 — Ventspils Free port administration / Ernst&Young Baltic, Ltd Analysis and provision of information in connection with the optimum technological solutions of the facilities to be constructed in Ventspils free port area: -Liquefied natural gas bunkerage terminal - Oil-contaminated waste-water treatment plants
07/11 — 08/11 Ventspils Free port administration / Developing of pre-design documentation for construction of liquid gas unloading and storage terminal in Ventspils
Baltic New Technologies, Ltd
01/16 — 05/16 Baltic New Technologies, Ltd / Preparation of documentation and environmental impact assessment report for Diesel fuel production facility construction (BALTIC CLEAN FUELS, Ventspils, Latvia).
02/09 — 03/09 “Rishon”, Ltd. / Development of 3D animation promo materials for railway platform and bridge for pipelines across Ogre river.
Neste Latvija, Ltd
05/19 — „Neste Latvija” Ltd. / „Neste Latvija” Ltd. light oil storage terminal Development of reconstruction design for the existing pump station and truck loading facility in order to secure technological operations with HVO oil product
05/19 — /
01/18 — 09/18 „Neste Latvija” Ltd. / „Neste Latvija” Ltd. light oil storage terminal Cargo identification system of Neste Latvija oil tank farm
05/17 — 06/17 „Neste Latvija” Ltd / „Neste Latvija” Ltd. light oil storage terminal Engineering works (software upgrade design and installation, SCADA controllers installation/re-installation) for tank level metering system ENRAF equipment substitution and ESD deactivation software updating
09/15 — 12/15 “Neste Latvija”, Ltd / „Neste Latvija” Ltd. light oil storage terminal Engineering works (development and installation of software, replenishment/re-installation of APCS controllers, comprehensive adjustment works)
07/15 — 08/15 “Neste Latvija”, Ltd. ” / „Neste Latvija” Ltd. light oil storage terminal Update of duplex data exchange applications between the company software and truck loading equipment
05/15 — 08/15 “Neste Latvija”, Ltd / „Neste Latvija” Ltd. light oil storage terminal Technical design for fuel marking system
03/15 — 12/17 “Neste Latvija”, Ltd. / „Neste Latvija” Ltd. light oil storage terminal Technical design for fuel marking system
09/14 — 05/15 “Neste Latvija”, Ltd. / ,„Neste Latvija” Ltd. light oil storage terminal Fuelling system modernization (electric installations, software development) for reconstruction of fueling island No.1 and construction of new track shoulders
04/14 — 09/14 “Neste Latvija”, Ltd. / ,„Neste Latvija” Ltd. light oil storage terminal Engineering design for fuelling system modernization (electric installations, software development) for reconstruction of fueling island No.1 and construction of new track shoulders
10/13 — 12/13 “Neste Latvija”, Ltd. / Neste Latvija” Ltd. light oil storage terminal Additive dosing solution for automatic loading system
07/12 — “Neste Latvija”, Ltd. / Riga terminal Terminal’s two-way data exchange between on-site application(s) and truck loading facilities TopTech MultiLoad II
09/11 — 12/11 “Neste Latvija”, Ltd. / ,„Neste Latvija” Ltd. light oil storage terminal Development of pre-design documentation for extension of pump station and pipeline route to the berth.
08/11 — 12/11 “Neste Latvija”, Ltd. / ,„Neste Latvija” Ltd. light oil storage terminal Modernization of Neste Latvia terminal refueling points No.232, 242, 252: development of engineering design, software, electric installation and commissioning works
01/10 — 12/10 “Neste Latvija”, Ltd. / Construction of road trucks handling facilities
12/09 — 08/10 “Neste Latvija”, Ltd. / APCS upgrading
10/09 — 12/09 “Neste Latvija”, Ltd. / Engineering design “Upgrading of road trucks filling capacity allowing adding of FAME additives into diesel fuel “.
Latvijas Dzelzceïð SJSC
05/16 — 09/16 Latvijas Dzelzceïð SJSC / Railway passenger infrastructure Design works for installation of the external power supply of the relocated Vaivari train station building.
11/15 — 12/15 Latvijas Dzelzceïð SJSC / Railway infrastructure Developing of design solutions for prevention ultimate limit technical condition of water supply grid in Zolitude (Riga, Latvia)
09/14 — 04/16 Latvijas Dzelzceïð SJSC / „RBSSKALS Bûvsabiedrîba un Leonard Weiss RTE” Railway passenger infrastructure Railway infrastructure modernization in Zolitûde, Imanta, Babîte, Bulduri, Dzintari, Pumpuri, Melluþi, Asari, Lielupe, Dubulti, Sloka, Vaivari, Majori, Olaine, Cukurfabrika, Jelgava stations’ areas.
06/14 — 08/15 Latvijas Dzelzceïð SJSC / RBSSKALS Bûvsabiedrîba” Ltd Cesis railway station Engineering design for construction of lifted railway platforms
02/14 — 05/14 Latvijas Dzelzceïð SJSC / Railway track reconstruction in Bolderaja station Work organization plan for relocation of external gas supply system
12/13 — 03/14 Latvijas Dzelzceïð SJSC / BMGS JSC Electrification of 2nd railway track of Skrîveri – Aizkraukle line Technical advisory and feasibility study of proposed technical solutions
04/13 — 08/13 Latvijas Dzelzceïð SJSC / Adaptation of Skriveri-Muldakmens electrification project solutions to the existing topographical layout
„B&B Investicijas”, Ltd
04/17 — 07/17 „B&B Investîcijas” LTD / Documentation for LNG storage facility construction and natural gas cogeneration station disposition in Gulbene region.
08/10 — 03/13 Riga fertilizer terminal” , Ltd / Mineral fertilizers short-term storage , and transhipment facilities in Free port of Riga Development of 1st and 2nd stage sketch design documentation, 1st and 2nd stage engineering design documentation and 3rd stage sketch design. Construction supervision
12/09 — 03/10 Riga fertilizer terminal” , Ltd / Mineral fertilizers short-term storage capacity and transhipment facilities in Free port of Riga Pre-design solutions
Priekule municipality
01/17 — 03/17 Priekule municipality / Draft design of Priekule sports centre swimming pool auxiliary building
05/11 — 11/12 Riga central terminal, Ltd / Pre-design solutions for Bulk cargo terminal in Riga, Krievu Sala area.
„Ventstone Complex”, Ltd.
06/17 — 07/17 „Ventstone Complex”, Ltd. / Design/engineering services for liquefied natural gas terminal and cogeneration heat station construction in Ventspils
10/13 — 11/13 „Ventstone Complex”,Ltd/ / Design engineering for liquefied natural gas terminal and cogeneration station construction in Ventspils, Ziemeïu str.21
JSC "Vilniaus architektūros studija"
12/17 — JSC "Vilniaus architektûros studija"/--- / Development of minimum scope design and construction design for multistorey residential building with leasable commercial premises
07/12 — 04/13 Latvijas Gaisa satiksme / Riga airport Design of voltage regulators for diesel rotor (0.4 kV stabilized power supply equipment) in ATC tower
Enefit Energiatootmine, Jsc
09/18 — 12/18 Enefit Energiatootmine, Jsc / Feasibility studies of relocation of main control panel of Baltic power station
12/12 — 01/13 PortTransServis Ltd. / Economic feasibility study for process equipment construction of pentane and isopentane receiving, storage and ship loading terminal
Novotrade Invest , Jsc
09/18 — 12/18 Novotrade Invest AS / Detailed construction design of new tank farm (10x2500 m3)
01/14 — 05/14 „Deloitte Latvia”, Ltd / Oil product terminals „OVI terminal” and„Woodison Terminal” Technical consultations for assessment of technical condition of „OVI terminal” (Tvaika str. 35, Riga) and „Woodison Terminal” (Tvaika str. 39, Riga)
Ultramar, Ltd
11/17 — 01/18 Ultramar, Ltd / Development of design documentation for Industrial and logistic complex for storage and transshipment of mineral fertilizers with storage facilities and railway infrastructure in Vistino, Leningrad region, Russia. Storage facilities with office and amenity bulding, conveyor lines for bulk mineral fertilizers and pipelines for liquid fertilizers routed from the storage complex to the berthing facilities.
03/14 — 05/14 Riga municipal police / Advisory on operative communication system design and hardware procurement tender : drafting of tender documentation and definition of bidding requirements
Borec, Ltd
04/20 — 04/20 Borec, Ltd / Provision of consulting services related to the requirements of the Latvian construction legislation
HT PH Tuapse – Nefteprodukt, Ltd
11/16 — 06/17 Tuapse-Nefteprodukt / Kross Tehnologii Ltd. Company infrastructure Editing of detailed design documentation for process pipelines located on oil jetties, full development.
08/16 — 05/17 Tuapse-Nefteprodukt / Kross Tehnologii Ltd. Company infrastructure Design and survey works for modernization of gas detection and equilibration systems, 2nd stage
07/16 — 08/16 Tuapse-Nefteprodukt / Kross Tehnologii Ltd. Company infrastructure Editing of technical documentation for reconstruction of process pipelines on oil berths, hydraulic surge protection system, replacement of pressure smoothing valves
02/16 — 04/16 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning works for oil-refining plant of the Tuapse oil refinery
01/16 — 05/16 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning works for modernization of the automatic filling station of Workshop No.1
10/15 — 12/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Editing of technical documentation for automatic fueling tank park equipping with automated oil products metering system.
06/15 — 12/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd Company infrastructure Procurement procedures for modernization of the automatic filling station of the Workshop No.1. APCS
06/15 — 10/15 Tuapse-Nefteprodukt" / Kombit Engineering Ltd. Company infrastructure Procurement procedures for reconstruction of oil berths’ process pipelines. APCS
06/15 — 07/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Heat supply systems (1st stage). APCS pre-commissioning
05/15 — 04/16 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Modernization of automatic filling station equipment of the Workshop No.1. APCS pre-commissioning
05/15 — 02/16 Tuapse – Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Modernization of the automatic filling station of the Workshop No.1. Pre-design study for APCS switching to automatic filling commercial accounting, design and research works
03/15 — 03/15 Tuapse – Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Modernization of automatic filling station equipment of Workshop No.1. Pre-commissioning works for the APCS software package. Export gasoline pipelines
12/14 — 12/14 Tuapse-Nefteprodukt / Kombit Engineering Ltd Company infrastructure Front-end engineering: Heating networks, 2nd stage
11/14 — 06/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning of process pipelines on Southern Mall (Jetties 1 and 2)
08/14 — 12/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Construction supervision: "Reequipment of fuelling system in production facility No.1
08/14 — 12/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Construction supervision: Modernization of treatment facilities. Reequipment of operating wells
08/14 — 12/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Construction supervision: Reconstruction of process pipelines on oil jetties. Surge relief system.
12/13 — 07/14 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for modernization of gas handling and gas equalizing sustems
11/13 — 03/16 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for transfering of oil-heating station from low-sulfur fuel oil to natural gas
11/13 — 12/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning of right bank water treatment facilities
10/13 — 12/14 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Construction supervision: process pipelines on Southern Mall jetties
10/13 — 06/14 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning of gas handling system and gas equalizing system
10/13 — 11/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for process pipelines from vehicle bridge to railway postern, substitution of pipelines on junction well
09/13 — 12/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning of Vertical steel tanks 20000 m3 ¹¹37,38
09/13 — 12/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning of Vertical steel tanks 10000 m3 ¹¹39,40
09/13 — 11/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-commissioning for process pipelines from vehicle bridge to railway postern , substitution of pipelines on junction well. APCS adjustment
09/13 — Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for re-equipment of pump station ¹7"
08/13 — Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Modernization of jety No.3. Supervision
08/13 — Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Petrochemicals’ fiscal metering system. Construction supervision
08/13 — Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Fire safety station ÒÏ-8À : Construction supervision
07/13 — 12/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for: Re-equipment of VST 10 000 m3 (¹¹32-36) for diesel fuel storage
07/13 — 11/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for automatic fueling area. Revision of detailed design documentation
01/13 — 08/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for modifying the VST 10000m3 for storage of vehicle gasoline and jet fuel (installation of pontoons)
12/12 — 09/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for transformer substation 10kV-6kV. Editing of technical documentation
11/12 — 01/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Development the declaration of intent for commercial accounting units on process piping from oil refinery
11/12 — 12/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for process piping from oil refinery to the facility tanks. Editing of technical documentation
11/12 — 12/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Supervision of construction of process piping from vehicle bridge to railway postern
10/12 — 03/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for modernization of gas handling and equalizing system
10/12 — 12/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructurec Supervision of construction of transformer substation 10kV-6kV
08/12 — 12/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Commissioning of process pipelines from Tuapse oil refinery to company storage tanks. Passing through Sochinskaya str. APCS.
07/12 — 09/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure APCS of units No.186 (1,2,3). Commissioning of overall APCS of the company
07/12 — 08/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design solutions for increasing storage capacity (drafting of declaration of intent)
06/12 — 09/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for integration of APCS of pump station No.5 into existing APCS
06/12 — 12/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for process piping from vehicle bridge to railway postern
05/12 — 07/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Reasearch and design of transformer substation 10êV/6êV
05/12 — 06/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for APCS and fire-fighting ACS of deep-water jetties 1a,1b.
04/12 — 06/12 Kombit Engineering Ltd. / Kombit Engineering Ltd. Company infrastructure Commissioning of oil technology process equipment of Tuapse oil refinery
04/12 — 06/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Commissioning of deep-water jetty No.1a interrelated with light and dark oil product transshipment facility
03/12 — 11/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for process piping on jetties No.1, No.2 (South pier)
03/12 — 07/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for Right shore treatment facilities. Sewerage pump station No. 7.
03/12 — 07/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for Right shore treatment facilities. (III start-up facility). APCS binding.
03/12 — 06/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for process pipelines from Tuapse oil refinery to company storage tanks. APCS binding.
03/12 — 06/12 Kombit Engineering Ltd. / Tuapse-Nefteprodukt Company infrastructure Research and design for process pipelines from traffic bridge to railway gallery. APCS binding.
03/12 — 06/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for process pipelines of tank farm No.2 (III start-up facility). APCS binding.
03/12 — 05/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Reasearch and design for overall APCS. Units 186-1,2,3. APCS binding design.
03/12 — 04/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for Vertical steel tanks 10000 m3 No.39, 40 with JET technology». Allocation of 1st start-up facility
03/12 — 04/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for transformer substation 10êV/6êV. Refurbishment of ÒÏ-13".
03/12 — Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for Left shore treatment facilities. Start-up facilities No.3, 4.
03/12 — 09/12 Kombit Engineering Ltd. / Tuapse-Nefteprodukt Company infrastructure Research and design for System of commercial accounting of oil products on oil jetties No.4, 5. Transformer substation 2õ630 êVà".
01/12 — 05/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for upgrading of Coalescent treatment facilities. Rearrangement of operating wells of protective drainage system
01/12 — 07/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for Company overall APCS. Integration of pump station No.5 into existing APCS. Process pipeline protection from overpressure and ensuring control over their operation.
01/12 — 06/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for upgrading of automated fire-fighting station and automated fire-fighting control system. Âðåìåííîå Temporary exclusion of VST-10000 m3 No.32 from overall APCS.
01/12 — 04/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Commissioning of APCS and automatic fire-fighting CS of deep-water jetties 1a and 1b.
01/12 — 02/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Research and design for process pipelines from traffic bridge to railway gallery (3rd stage). Junction points.
01/12 — 04/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for process pipelines from Tuapse oil refinery to company storage tanks. Switchboard room
12/11 — 12/11 /
11/11 — 02/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for deep-sea terminal. Upgrading APCS with hydroblow protection system
09/11 — 06/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for reconstruction of process pipelines on jetties. Completion.
08/11 — 08/13 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for object’s heat networks
08/11 — 12/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for light oil pump station No.5. Integration with existing APCS. Units No. 186 (1,2,3)
07/11 — 11/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for Automated industrial process control system including control room of tank farm No.1. System integration into current APCS of pump station No.5
07/11 — 09/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for Vertical Steel Tanks 10000 m3 No.39,40 with JET technology»
07/11 — 08/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Commissioning of automatic fire-fighting control system for VST 10000 m3 Nr.32, 33, 34, 35, 36
06/11 — 08/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for deep-sea gas blowing control system
06/11 — 08/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure APCS commissioning for 10000 m3 VST Nr.32, 33, 34, 35, 36
06/11 — 10/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for process pipelines from prefabricated bridge to railway gallery (3rd stage)
06/11 — 09/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Commissioning of process pipeline excess pressure protection system for indusctrial process APCS Project
06/11 — 09/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey for process pipelines of tank farm No.2
05/11 — 02/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for refurbishment of berth No.3
05/11 — 02/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for refurbishment of berth No.6
04/11 — 03/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for oil fiscal metering unit. Volume metering and quality detection system on berths No.4, No.5
04/11 — 08/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd Company infrastructure Design and survey works for fire-fighting depot. Transformer substation ÒÏ-8À .
04/11 — 07/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for company communication system (5th stage). External communication networks. Multifunctional industrial communication system.
04/11 — 05/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for APCS of light oil pump station No.5. Development of self-contained system.
03/11 — 03/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-design works for deep-sea berth 1A designed for transshipment of dark and light oil in Tuapse sea port. Amending design and estimate documentation for metering unit
02/11 — 06/12 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for oil technology of Tuapse oil refinery
02/11 — 06/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd Company infrastructure Company APCS including tank farm control room (5th stage). Commissioning of automatic reactive power compensation system for 6,0 and 0,4 kV network.
01/11 — 07/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd Company infrastructure Design and survey works for APCS development Project : "VST-10000 ì3 ¹¹39,40.”
01/11 — 06/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for APCS development for "VST-20000 ì3 ¹¹37,38.” (VST –Vertical Steel Tank)
01/11 — 03/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Pre-design solutions for refurbishment of gas recovery and gas surge systems.
11/10 — 10/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for 10 kV/6kV transformer sub-station
11/10 — 08/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for staff canteen construction project
11/10 — 07/11 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Design and survey works for Control Room project
11/10 — 12/10 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Adjustment and commissioning of operational process pre-set control system for storage tanks No.1-6»
07/10 — 12/10 Tuapse-Nefteprodukt / Petroproekt Ltd.. Company infrastructure Design and survey works for development of automatic operational process control system and automatic fire-fighting control system of sea terminals 1a, 1b.
Rosneftbunker, JSC
05/16 — 12/16 Ust-Luga Oil, JSC / Multifunctional Port terminal “Ust-Luga” Process setup for liquid cargo storage base (3rd stage). Light oil railway unloading facility No.3
05/16 — 07/16 st-Luga Oil, JSC / Multifunctional Port terminal “Ust-Luga” Analysis and editing of the process regulations of the railway loading facilities No.1 No.2 (considering the option of vacuum gas oil unloading).
12/15 — 02/16 Ust-Luga Oil, JSC / Multifunctional Port terminal “Ust-Luga” Liquid cargo storage base construction , 4th stage. Automatic control system. Engineering design for of high viscosity oil unloading railway facility No.4. Modernization, incl. relocation of APCS equipment
04/15 — 10/15 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Liquid cargo storage base construction, 4th stage. Automatic control system. Engineering design for of high viscosity oil unloading railway facility No.4 with related infrastructure. APCS software package upgrade.
03/15 — 04/15 Rosneftbunker, Jsc/ / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” WEB-server software upgrading affecting the railway unloading facility No. 4 mimic diagram
03/15 — 04/15 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Pre-commissioning works: Liquid cargo storage base. Railway unloading facility No.4. APCS
01/15 — 04/15 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Pre-commissioning works: Liquid cargo storage base. Railway unloading facility No.4. APCS
01/15 — 02/15 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Pre-commissioning works: Liquid cargo storage base. Railway unloading facility No.4
10/14 — 12/14 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Design documentation: Liquid cargo storage base. Railway unloading facility No.3.Reconstruction. APCS
09/14 — 10/14 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Front-end engineering: relocation of oil unloading facilities’ No.1, 2, 3 APCS hardware from unloading control room to maintenance room
02/14 — 07/14 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” APCS of unloading facility No.4 for viscous oil products
02/14 — 04/14 Rosneftbunker, Jsc / VAMI Avtomatika Ltd. Multifunctional Port terminal “Ust-Luga” Survey of design documentation, pipeline system and equipment for process setup of light oil transshipment unit (Liquid cargo storage base)
11/13 — Rosneftbunker, Jsc / Kombit Engineering Ltd Multifunctional Port terminal “Ust-Luga” Supervision of viscous oil unloading facility No.4 and power units No. 4, 5.
05/13 — 12/13 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Design of Liquid cargo stograge base in Ust-Luga sea port. Unloading railway station No.4 for high-viscosity products, with infrastructure
05/13 — 08/13 Rosneftbunker, Jsc / VAMI Avtomatika Ltd. Multifunctional Port terminal “Ust-Luga” Examination of design documentation, pipeline system and equipment for process setup of light oil transshipment facilities
04/13 — 04/13 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Examination of thermal balance in mazout unloading stations ¹1,2 and in automated thermal oil heating station during oil and petrochemical unloading at maximum capacity
11/12 — 06/13 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Process setup and commissioning of light oil unloading facility No.3 of pump station No.10.1
09/12 — 11/12 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” APCS commissioning for light oil unloading facility No.3 of pump station No.1
09/12 — 11/12 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Editing of technical documentation for light oil unloading facility No.3 of pump station No1
08/12 — 11/12 Rosneftbunker, Jsc / VAMI Avtomatika Multifunctional Port terminal “Ust-Luga” Survey of design documentaion for process setup of mazout facility in framework of 2nd stage of bulk cargo complex construction
06/12 — 06/12 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Re-development of APCS software for mazout unloading railway platforms No.1, No. 2
02/12 — 06/12 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Development of detailed design documentation for hot water, nitrogen and air supply of railway loading platforms No.1, No.2
01/12 — 07/12 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Editing of detailed APCS design documentation for railway unloading platform No.3 with light oil unloading pump station No.1. Object integration with APCS.
12/11 — 11/12 Rosneftbunker, Jsc / Kombit Engineering Ltd. Multifunctional Port terminal “Ust-Luga” Development of process regulations for commissioning and startup of facilities constructed in framework of 1st and 2nd stage of bulk cargo complex storage facilities
06/11 — 07/11 Rosneftbunker, Jsc/ / Petroproekt, Ltd Multifunctional Port terminal “Ust-Luga” Re-drafting of engineering documentation for light oil unloading pump station
10/10 — 02/11 Rosneftbunker, Jsc / Petroproekt, Ltd Multifunctional Port terminal “Ust-Luga” Design documentation for standby power supply system of emergency and process reserved quota power consumers at railway loading/unloading facilities 1,2,3.
04/10 — 11/11 Rosneftbunker, Jsc / «SPIK SZMA» JSC Multifunctional Port terminal “Ust-Luga” Design documentation and software development for automatic control system of fuel oil unloading facility No.2 ,
12/09 — 04/13 Rosneftbunker, Jsc / Petroproekt, Ltd Multifunctional Port terminal “Ust-Luga” Editing of design project documentation after completion of construction supervision of loading/unloading facility No3, pump station, foot bridges connecting loading/unloading facilities No. 1, No.2, No.3.
12/09 — 09/10 Rosneftbunker, Jsc / VAMI Avtomatika Multifunctional Port terminal “Ust-Luga” Design project documentation of Automatic fire-fighting process control system of bulk cargo storage facilities.
10/09 — 12/09 Rosneftbunker, Jsc / Petroproekt, Ltd Multifunctional Port terminal “Ust-Luga” Preparing of operation charts and modes of mazout unloading facility. Preparing of operational manuals for unloading facility equipment units. Composing of manuals of oil products heating and unloading operations.
08/09 — 09/09 Rosneftbunker, Jsc / Petroproekt, Ltd Multifunctional Port terminal “Ust-Luga” Development of comprehensive testing program of equipment operation and control systems of mazout unloading facility. Preparing of process manual for mazout unloading facility.
05/09 — 09/09 Rosneftbunker, Jsc / Multifunctional Port terminal “Ust-Luga” Engineering design of pedestrian overpasses over railway unloading platforms.
03/09 — 05/09 Rosneftbunker, Jsc / Multifunctional Port terminal “Ust-Luga” Mazout unloading railway platform No.1. Construction supervision
02/09 — 12/09 Rosneftbunker, Jsc / Multifunctional Port terminal “Ust-Luga” Light oil unloading railway platform No.2. Construction supervision
01/09 — 11/13 Rosneftbunker, Jsc / Multifunctional Port terminal “Ust-Luga” Mazout unloading railway platform No.2. Construction supervision
07/08 — 12/11 Rosneftbunker, JSC / Multifunctional Port terminal “Ust-Luga” APCS detailed design development for railroad loading/unloading platform No.1. “Fluid cargo complex” project
07/08 — 12/09 Rosneftbunker, JSC / Multifunctional Port terminal “Ust-Luga” APCS detailed design development for railroad loading/unloading platform No.1. “Fluid cargo complex” project
„Ust-Luga company”JSC
08/16 — 11/16 „Ust-Luga company”JSC / Multifunctional Port terminal “Ust-Luga” Pre-design works for cost evaluation for the construction of Multipurpose Fertilizer Transshipment Complex in Ust-Luga commercial port area
“Aviacionnie Tehnologii Topliva”, JSC
02/18 — 03/18 Sibintek Ltd. / Knevichi Airport Revision of the SCADA design documentation and SCADA pre-commissioning of Knevichi airport fueling unit (Artem, Russia)
10/17 — 12/17 Aviacionnie Tehnologii Topliva JSC / Sheremetyevo Airport Testing of the existing equipment and follow-up revision of SCADA documentation of road tanks unloading points and filling of the airfield fueling truck.
08/16 — 12/16 cionnie Tehnologii Topliva JSC / NPO Aviatehnologia Sheremetyevo Airport Equipment procurement, assembling and commissioning works related to the technical upgrading of the APCS software package for the alternative fuel and oil storage facility and Gazpromneft - Aero Sheremetyevo LLC fueling point.
08/16 — 11/16 Aviacionnie Tehnologii Topliva JSC / Sheremetyevo Airport Upgrading of the APCS software package for the alternative fuel and oil storage facility and Gazpromneft - Aero Sheremetyevo LLC fueling point.
06/15 — 07/15 Tuapse-Nefteprodukt / Kombit Engineering Ltd. Company infrastructure Heat supply systems (1st stage). APCS pre-commissioning
12/14 — 02/15 Aviacionnie Tehnologii Topliva JSC / Sheremetyevo Airport Concept design of POL storage facility
11/14 — 07/15 Aviacionnie Tehnologii Topliva JSC / Neftehimstroy JSC Sheremetyevo Airport Reconstruction of Central fuelling unit in Sheremetyevo airport. Preliminary/Engineering design
06/13 — 02/17 Aviacionnie Tehnologii Topliva JSC / Kolcovo airport Reconstruction design for POL storage area in Kolcovo airport
05/13 — 09/13 Aviacionnie Tehnologii Topliva JSC / Domodedovo airport Design of pump and filtering station providing jet fuel transportation to CAFS and fueling point in Domodedovo airport
03/13 — 09/13 Aviacionnie Tehnologii Topliva JSC / Sheremetyevo Airport Design of development concept for Sheremetyevo fuelling facility POL storage
03/13 — Aviacionnie Tehnologii Topliva JSC / Development of engineering binding for oil product metering and quality control system of POL storage
02/13 — 03/13 Aviacionnie Tehnologii Topliva JSC / Pulkovo Airport Disposition of land plots No.1, No.2, No.3, main buildings and constructions on general layout diagrams
11/12 — 08/14 Aviacionnie Tehnologii Topliva JSC / Sheremetyevo Airport Design works for administration and catering building
11/12 — 12/12 Aviacionnie Tehnologii Topliva JSC / Sheremetyevo Airport Design of development concept for Sheremetyevo fuelling facility POL storage development until 2030
11/12 — Aviacionnie Tehnologii Topliva JSC / Sheremetyevo Airport Design works for pre-platform fueling point located in Sheremetyevo-1 segment (2nd stage)
10/12 — 05/13 Aviotehnologia ASP JSC / Sheremetyevo Airport Commissioning and integration of oil product metering and quality control system into current automatic process control systems of alternative POL storage
09/12 — 03/13 Aviacionnie Tehnologii Topliva JSC / „Krimsk” fuelling facility POL storage Preliminary and detailed design documentation for construction of „Krimsk” fuelling facility POL storage
08/12 — 10/12 TZK Sheremetyevo JSC / Sheremetyevo Airport Preliminary studies and introduction and development concept for jet fuel suply APCS
03/12 — 07/12 Aviotehnologia ASP JSC / Knevichi Airport Engineering solutions for process module equipment (manufactured by Aviotehnologia ASP JSC) located in receiving and active storage facilities of Knevichi airport
09/11 — 06/12 Aviotehnologia ASP JSC / Sheremetyevo Airport APCS and Accounting equipment installation supervision and commissioning for alternative oil and lubricants storage in Sheremetyevo airport
04/11 — 08/11 Aviotehnologia ASP JSC / Knevichi Airport Installation supervision, commissioning and certification of metering methods at all metering and accounting points of airport loading facility
04/11 — 07/11 Aviotehnologia ASP JSC / Knevichi Airport Procurement of APCS and Accounting equipment and frequency control power distribution boards for airport loading unit pumping facilities
11/10 — 08/11 Aviacionnie Tehnologii Topliva JSC / Petroproekt Ltd. Sheremetyevo Airport Design of APCS and automatic accounting system of alternative oil and lubricants storage in Sheremetyevo airport
11/10 — 07/11 Aviacionnie Tehnologii Topliva JSC / Petroproekt Ltd. Sheremetyevo Airport Equipment procurement for APCS and automatic accounting system of alternative oil and lubricants storage in Sheremetyevo airport
09/10 — 01/11 Aviacionnie Tehnologii Topliva JSC / Knevichi Airport Construction design for fueling facility in Knevichi airport
12/08 — 02/12 “Aviacionnie Tehnologii Topliva”, JSC / Sheremetyevo airport Design works within the framework of fuels-lubes storage of fueling station in Sheremetyevo airport.
“Karelskiy Okatysh”, JSC (Russia)
01/20 — Karelsky Okatysh JSC / Karelsky Okatysh Designer supervision of technical upgrade of the raw in the pelletizing process for the site (Karelsky Okatysh JSC)
08/19 — 12/19 Karelsky Okatysh JSC / Karelsky Okatysh Upgrade of the dispatching monitoring and control system of ore concentrate and pellets production process (Karelsky Okatysh JSC)
05/19 — 06/19 Karelsky Okatysh JSC / Karelsky Okatysh Development of design documentation of the lime production facility of Karelsky Okatysh JSC
05/19 — Karelsky Okatysh JSC/ Spb Giprosaht Ltd / JSC/ Spb Giprosaht Ltd Karelsky Okatysh Construction of ore uncovering equipment of conveyor ore transportation technology for the Central section of the Kostomuksha ore deposit of detailed design documentation of the 1st conditional stage of works
04/19 — 06/19 Karelsky Okatysh JSC / Karelsky Okatysh Technical upgrade of crushing and sorting facility of the Central quarry (Karelsky Okatysh JSC)
03/19 — 10/19 Karelsky Okatysh JSC / Karelsky Okatysh Technical upgrade of raw pelletizing process site (Karelsky Okatysh JSC).
03/19 — 06/19 Karelsky Okatysh JSC / Karelsky Okatysh Technical upgrade of fuel oil heaters using thermal oil and induction heating in the oil product storage warehouse area
02/19 — 04/19 Karelsky Okatysh JSC / Karelsky Okatysh Technical upgrade of the diagram of connection of water heaters to existing network pipelines (Karelsky Okatysh pellet processing facility boiler house).
10/18 — 07/19 Karelsky Okatysh JSC / Karelsky Okatysh SCADA commissioning works as a part of general commissioning of refuse ore treatment facility No. 2 (Karelsky Okatysh JSC)
06/18 — 07/18 Karelsky Okatysh JSC / Karelsky Okatysh Design of foundations for the construction of a crushing and sorting facility of the Kostomuksha ore deposit
04/18 — 09/18 Karelsky Okatysh JSC / Karelsky Okatysh Development of detailed design documentation, application software for automatic control system for refuse ore treatment facility No. 2; delivery of equipment, supervision, adjustment
04/18 — 04/18 Karelsky Okatysh JSC / Karelsky Okatysh Audit of the design documentation developed by Beloozersk electromechanical plant for installation of 3 steam boilers with low-temperature fluidized bed furnace applying solid fuel (peat and wood chips), within the dimensions of the existing boiler house foot print; construction of a fuel storage unit with a fuel supply system.
09/17 — 10/17 Karelsky Okatysh JSC / Karelsky Okatysh Feasibility study for re-equipment of fuel oil heating systems of Karelsky Okatysh ore pellet processing facility
05/17 — 07/19 Karelsky Okatysh JSC / Karelsky Okatysh Designer’s supervision of construction and according adjustment of design documentation for refuse ore treatment unit No. 2 (Karelsky Okatysh JSC).
02/17 — 07/17 Karelsky Okatysh JSC / Karelsky Okatysh Detailed design documentation for providing of power supply fot tailing thickening units No.1, No.2.
01/17 — 10/17 Karelsky Okatysh JSC / Karelsky Okatysh Detailed design documentation of tailing thickening unit No.2
05/16 — 11/16 Karelsky Okatysh JSC / Karelsky Okatysh Design of tailing thickening unit No.2
01/16 — 05/16 Karelsky Okatysh JSC / Karelsky Okatysh Commissioning of SCADA for tailing thickening unit No.1
06/15 — 11/15 Karelsky Okatysh JSC / Karelsky Okatysh Pre-design (front-end) works for the construction of Tailing thickening unit No.2
05/15 — 08/16 Karelsky Okatysh JSC / Karelsky Okatysh Construction supervision for tailing thickening unit (module No.2)
04/15 — 04/16 Karelsky Okatysh JSC / Karelsky Okatysh Commissioning of tailing thickening unit SCADA
06/14 — 10/14 Karelsky Okatysh JSC / Design for reequipment of tank heating system using thermal oil
03/14 — 07/15 Karelsky Okatysh JSC / Design and supervision: Tail thickening unit
03/12 — 07/12 Karelsky Okatysh JSC / Karelsky Okatysh POL storage Development of detailed design documentation for POL storage reconstruction in order to expand diesel fuel storage capacity.
03/12 — 05/13 Karelsky Okatysh JSC / Karelsky Okatysh POL storage Development of design documentation for POL storage reconstruction in order to expand diesel fuel storage capacity
03/12 — 07/12 Karelsky Okatysh JSC / Karelsky Okatysh POL storage Development of detailed design documentation for replacement of diesel fuel pumping equipment of POL storage facilities
05/11 — 10/12 Karelsky Okatysh JSC / Pre-design solutions for feasibility studies of boiler house construction/reconstruction
04/11 — 01/12 Karelsky Okatysh JSC / TekomProf Ltd. Design, adjustment and putting into operation of APCS for railway unloading facility
04/11 — 08/11 Karelsky Okatysh JSC / TekomProf Ltd. Completing and procurement of APCS equipment railway unloading facility
05/10 — 09/10 Karelsky Okatysh JSC / Tapflo Ltd Design of solutions for pump anchoring at mazout heating units of railway unloading facility
02/10 — 12/10 Karelsy Okatysh, JSC /
  • Development of design and engineering documentation for reconstruction of mazout unloading system
  • Design of refurbishment of condensate gathering system of central boiler plant
  • Development of operation procedure for railway unloading facility applied for manual unloading of oil and lubricants. Commissioning , puting into operation and  operational testing of the facility
04/09 — 05/09 Karelsy Okatysh, JSC / Front-end engineering works for iron-ore slurry pre-heating system using heated vapour in slurry mixing units with following transportation of the heated mass by railway transport
“Zhirovoy Kombinat” JSC (Saratov, Russia)
07/17 — 08/17 “Zhirovoy Kombinat” JSC (Saratov, Russia) / Consultations on optimizing the process of heating and unloading of saturated fats from railway tanks
08/10 — 10/10 Baltiyskiy Universalniy Terminal Ltd / Ust-Luga design and engineering company Oil storage and bunkerage terminal in Ust-Luga sea port Development of pre-design solutions and technical requirements for off-site utilities connection
"Batumi oil terminal", Ltd (Georgia)
01/16 — 10/16 Batumi oil terminal, Ltd / Conti Chemical Company Ltd Batumi oil terminal, Ltd Modernization of the Batumi Oil Terminal Railway loading unit No. 2 for the reloading of heavy fuel oil (design and cost estimate documentation, SCADA design and procurement, commissioning works)
07/15 — 08/15 Batumi oil terminal, Ltd / Conti Chemical Company Ltd Batumi oil terminal, Ltd Modernization of railway loading units No.2 , No.4 for the supply of heavy fuel oil (survey, development of design specification)
01/11 — 10/11 Batumi oil terminal, Ltd / Fabregas Equipment Ltd. Batumi oil terminal, Ltd Detailed engineering design for oil vapor odor control unit
01/11 — 10/11 Batumi oil terminal, Ltd / Fabregas Equipment Ltd. Batumi oil terminal, Ltd Detailed engineering design for vapor recovery unit
01/11 — 10/11 Batumi oil terminal, Ltd / Fabregas Equipment Ltd. Batumi oil terminal, Ltd Detailed engineering design for industrial and rain waste water treatment unit
01/11 — 10/11 Batumi oil terminal, Ltd / Fabregas Equipment Ltd. Batumi oil terminal, Ltd Detailed engineering design for industrial and rain waste water treatment unit
01/11 — 10/11 Batumi oil terminal, Ltd / Fabregas Equipment Ltd. Batumi oil terminal, Ltd Detailed engineering design for industrial and rain waste water treatment unit
02/10 — 07/10 Batumi oil terminal, Ltd / Conti Chemical Company”, Ltd Engineering design of oil vapour trasfering from oil tankers and removing of mercaptan/H2S from oil vapours during tankers loading on berth No.1 and tandem loading/unloading operations.